Can we have a Capital project with Opex and Capex WBS and have no budget limit on OPEX WBS.

May 19, 2017 at 05:11 PM

60

avatar image
Former Member

Hello Experts,

Greetings.

I have a requirement from Client to configure a Capital Project to contain an Opex and Capex WBS [1 primary - Level 1 WBS and 2 Secondary - Level 2 WBS (Capex and Opex)]

Now the requirement is that if i allocate a budget (say) 1000 AUD to the Primary - Level1 WBS

They wish to allocate this entire amount to Capex WBS. As for the Opex WBS, they dont want any limitation/ constraint to the limit.

Currently Standard SAP allows me to allocate (say) 1000 AUD to primary WBS and then i am at the liberty to distribute this amount among the 2 secondary WBS. They want that this entire amount is to be allocated to the Capex WBS and none to the Opex WBS however this shouldn't prevent us from posting costs to the Opex WBS.

Is there a way to achieve this. Thank you in advance.