on 05-19-2017 3:32 PM
When ever I raise a PR the PO gets split in two POs. Which my supplier doesn't accept. They want a single PO for an order. But since last few days SAP is giving me 2 different PO for same PR. Certain line items are in one PO while others are in different PO
Hi Zahid ,
Under Document Settings--> Per Document --> Purchase order in Document and under that Un-check the Split Purchase Order to avoid split PO.
Regards:
Balaji.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.