Plant Maintenance Order: FI Plan Integration

73 Views

We have configured PM orders to accept cost planning entries on various plan versions similar to the capabilities of Internal Orders. Internal Orders have a setting that allows for plan integration with FI. We would like to have FI plan integration work with PM orders but they don't appear to allow for this. If you have found a way to have the FI plan integration function work with PM orders please describe what configuration changes you made to allow for this. Regards.