RA cost based method - how to exclude cost element from POC calculation but include in actual cost ?

theot_vincent
Discoverer
0 Kudos

Hi,

In PS, with the Result Analysis cost based method (3), how can we manage a cost (isolated on a dedicated cost element) that have to be excluded from the POC calculation (POC that will generate the revenue calculated) but included in the actual costs (e.g category VLCO in COSB table) ?

Thanks

Vincent