Hi All,

I have a basic doubt, when i run standard cost estimate for the next period, i know i can mark it and i cant release it, as the system says its too early to release. Which period does it looks into is it from MM or FI period or ....

When i release the standard cost estimate in the month beginning say March 1st -period 12, is the revaluation entry posted for the current for the period of March (12) or February (11).

I have a requirement saying the revaluation entry is to be posted for the previous period, say February and not March when i release the standard cost estimate for the period

of march. Where in i need to show my revaluation stock entries in my balance sheet for the previous period and not for the current period - 12.

Any body could you throw some light on this, functionally and

technically. How to address this in the system.

Thanks in advance