GR for Scheduling agreement

Former Member
0 Kudos

I am getting an error " doc # -


does not exist" when I am trying to do a Goods receipt for a scheduling agreement using MIGO. I have tried with different SA #- but same error. In MIGO I am using GR- PO #. What am I doing wrong?

Thanks

Raj Patel

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Raj,

You have to make a delivery schedule first & enter the todays date for delivery.

Hope it will help you.

Regards,

Manish Agarwal

Don’t forget to reward if useful ans.

Former Member
0 Kudos

Charlie:

do I need to make a delivery schedule first?

Thanks

Raj

Former Member
0 Kudos

yes , becasue SA without delivery schdule is nothing but just like contract.you have to have that and based on that you do GR

Former Member
0 Kudos

you are not doing anything wrong but the GR against the SA is bit interlligent.......means if you are trying to GR today but the GR date in SA is not due o today then system will trhough the same error which oyu have mentioned

to test wothout arror make your SA delivery date today and receive...it will allow GR.