Dear SAP Experts

I'm having a problem with cost analysis of process orders.

The situation is as below:

- Cost estimate exists

- BOM has not changed after cost estimate

- All components are included in BOM and captured in cost estimate

- Confirmations are OK and GR done.

problem is:

- Some components have an incorrect target quantity in KKBC_ORD. for example 100 KG instead of 120 KG "although it's captured correctly in cost estimate"

- Some components does not have a target quantity or cost at all "although it's captured in cost estimate"

- The rest of components have target costs calculated correctly without problems

What should I check for?