available funds in going to negative in sap Funds management (former Budgeting)

0 Kudos

Hi Experts -

we are having a issue in the system. our available budget sometimes goes into negative after certain transactions are performed. system allows to post transactions even though there is not enough budget. the report FMRP_3FMB4006 shows the negative figures in the column "available budget". the situation is getting corrected after users post some additional budget to cover the deficit. our AVC settings speak about error once we reach 100%. we have tried to simulate/mimic the situation but could never encounter such a situation in our test systems. has any body ever encountered such a situation ..

regards

Murali Tirupathi

5 REPLIES 5

iklovski
Active Contributor
0 Kudos

Hi,

Do you mean that you have negative available budget after overconsumption or that you are able to inscribe negative budget or make it negative when there is no consumption? If the second is correct, then consult note 983853. Otherwise, there is something wrong with your AVC ledger. You can consult note 573409 in order to get a grasp what could be the cause of it.

Regards,

Eli

0 Kudos

Hi - Thanks Eli for your response.

i mean the system is sometimes allowing for transactions beyond the available budget e.g when i have

released budget 100

distributable 100

assigned is 110

available -10

commitments/act 110

system is allowing for budget commitments transactions beyond available.

but as you had suggested i will check and revert back.

regards

Murali

0 Kudos

Hi - Eli

we have been observing the system closely after we had one issue again of system going beyond ( available budget in minus) last week

we have observed that this issue was during STO process where we have 351 MT (issuing plant) and 101 MT ( receiving plant) involved in moving material. we are now checking to see if any movement in material price after 351MT before 101 MT on account of moving average price valuation strategy is causing this.

thanks and regards

mar_novalbos
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi

From your description, pointing to Former Budgeting, I would suggest note 142866 - Availability control for goods receipt in FM .

Kind regards

Mar

0 Kudos

Hi ALL - thanks for your responses, i would like to let know everyone that we could analyze the negative available budget was because of STO process. when the STO is created system was committing budget as per unit price available at that time. if the document is prepared for more than available system will throw error at this stage. but during consumption system will check the price in material master and consume budget as per unit price available at that time. the availability control was not checking budget during consumption. consequent to this if there is a difference between moving average price at the time of STO creation and issue of material, the system to the extent of difference was posting negative.

thanks and regards