on 05-17-2017 9:58 AM
Hi Andreea,
As suggested check the goods movement qty for 101 mvt type in order goto---Document goods movement tab.And aslo check in tcode COGI for for this order with some error in goods movement.
Regards.
Swapnil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Andrea,
Have you checked the COGI?, you may have confirmed the full qty but it is possiblel that due to some error the goods movement is not posted.
so as suggested check the goods movement for the order.
regards,
Solomon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Andreea,
The total quantity is the planned quantity from the production order, the delivered quantity represents the quantity that has been posted against the order from the goods receipt and the short/Esc Rcpt is the difference between what you planned to receive and what was actually received. I think if you check the material movements and the confirmation against the production order you'll see that the GR (101) and the confirmed quantity will be 9 PC.
We use process orders not production orders but here's what I see when the GR and Confirmation quantity is less than the planned quantity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.