SCEM Implementation

Former Member
0 Kudos

We are going to implement the SCEM with the customs fields to meet our requirements. We checked the standard 4cubes and 3 ODS with lot of Abap update routine in each of the cube from ODS .

Now we are adding 20 to 50 customs fields to these standard cube and ODS .We are estimating how much work and how many hours it take to complete this work.

Could any of expert let me know how to proceed this work how do I estimate it.

Thanks in advance

Kitu

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member184494
Active Contributor
0 Kudos

Kitu,

Welcome to SDN....

What you could look at for estimation :

1. Nature of customization of extractor - build your own / customize decisions

2. Complexity of the system - Did you mean SCM or SEM - some systems esp CRM systems / HR systems need a special breed of ABAP

3. Data voulmes for the same

4. ABAp code in BW / transformations

5. Possible migrations ?

6. Modeling and data volumes

7. Report development

Arun

Hope it helps...