Skip to Content
-1

Components of a BOM driven by a sales order

Hello,

Is there any possibility to make the components of a particular BOM to be driven by a Sales Order only and not by demand?

If I change those strategy material into make to order will solve the issue?

Thank you,

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • May 18, 2017 at 02:38 PM

    Hi Andrea

    I did not understand your question. What do you mean by demand? Do you want to explode the BOM only when you have a sales order and not with an independent requirement? If this is the case, why are you using independent requirements?

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 18, 2017 at 03:48 PM

    Andrea,

    you wont achieve this solution just by changing the strategy. Strategy just derives how we are managing this material.

    it do not specify what management is set up for it.

    There are multiple ways to set this up:

    1 Variant configuration.

    2. Sales order BOM

    3. Customization and code change when BOM is attached to Production order/ Process order at time of creation.

    Based on your business requirement and how you manage the material will derive the solution.

    Thanks

    Anand

    Add comment
    10|10000 characters needed characters exceeded

  • May 20, 2017 at 05:55 AM

    Hi Andrea

    Components of BOM are better controlled By sales order through Variant Configuration (VC) Strategy Group 25.

    With Regards

    Puneet Puri

    Add comment
    10|10000 characters needed characters exceeded

  • May 23, 2017 at 07:10 AM

    Hi Andrea,

    I suggest, you need to create two different production version. and whenever you create PIR or sales order, you can select the production version at the time of creation of PIR. in MD62 > schedule line tab go to setting > production version.

    hope this will solve the question.

    regards,

    Solomon

    Add comment
    10|10000 characters needed characters exceeded