on 02-12-2007 9:42 PM
Hello friends,
I have a problem during creating a PO also PO requisition. During my work, the system is reporting this error message:
"Budget for all Years under year-based commitment update of value type Purchase order".
I thing the problem is caused by some wrong year end closing activities or by the budget.
I am hopeless. Thanks for your help,
Charlie
check transaction OPS9 if your are not working with PS system then check the config in KOAB and OKOB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
make sure you rinternal order in this case is not out of budget
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you getting reqs against the internal order then it is related to controlling mans you have to check the settings for controlling which i have suggeted
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is the question for FI or PS person....ask them they will help you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.