Hi,

Am using the BAPI "<b>BAPI_MOSRVAPS_SAVEMULTI3</b>" to create Planned Orders. There is a problem with one of the parameters "<b>ORDER_START_DATE</b>" . Though am passing the value for this field, still the orders are getting created with order end date as the date I've passed as start date.

I populated both the values for start and end date still the problem continues. The strategy profile is configured as Planning in <b>Forward Direction</b>. I'm passing both <b>order_head</b> and <b>order_head_x</b> tables.

Please suggest what can be done regarding this.

<b>Thanks in advance

Pradipta Ku. Mishra</b>

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Pradipta - check that the planning_mode field in the planning_mode_usage import parameter is set to 1 to use the product master planning setting. Also note if you are entering an explosion date is entered this may alter the start/end date.

Hope this helps

Andy