Purchase Requisition delete and recreate after MRP run MD50 with planning mode 2

Hello Experts,

While MRP run using T code- MD50 system deletes and recreate PR and Planned order. I have select MRP control parameter planning mode as "2" Re-explode BOM and Routing and also remove selection of "Also planned unchanged components" from Process control parameter.

As we have selected all these parameters system should delete and recreate PR and Planned order only for changes in BOM. Instead of that system is deleting and recreating all PR ans Planned orders with reference to BOM.

My requirement is system should not delete and recreate for any unchanged materials. System only delete and recreate procurement proposals for changed materials.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 16, 2017 at 03:29 AM

    Hello

    I suggest you to read carefully SAP Note 412736. In the section Net calculation, you will find an explanation about the reusability of the replenishment proposal, where there is a detailed explanation of when a replenishment proposal is deleted and recreated by MRP and when it can be reused.


    Regards,

    Caetano Almeida