on 02-07-2007 4:26 AM
Dear CO/PS Experts
I am working with Project system Result analysis/settlement.
Result analysis has three stages RELE, FNBL and TECO
We have ddone the customisation settings in such a way that WIP is created when the project status is RELEASED and reversed in FNBL stage.
AFter reversing the WIP in FNBL stage we expect the RA/Settlement to post all expenses/revenues to PSG segment which is not happening.
Thanks and Regards
Subbu
+91 9910372277
Hello Subbu
We have a WBS and is assigned to sales order.
Now we want to know how to set up FNBL in WBS automatically once the sales order and billing is done.
Can you explain the configuration of RA. It will be really helpful.
We settle WBS both for revenue and cost.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.