Hello gurus,

How a WT of, let say 10 Cartons, can be split into 10 WT of 1 cartons with an Pick-HU assign to it ?

Thanks for you reply !

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 18, 2017 at 04:03 AM

    hi,

    You can do so under the following path :

    Extended Warehouse Management --> Master Data --> Define Storage Type

    For your storage type maintain "Round Whole Units" as 2 (Round down WT Quantity to single unit).

    This can be maintained for warehouse process type too under :
    Extended Warehouse management --> Cross Process Settings --> Warehouse Task --> Define Warehouse Process type.

    Regards,
    Garima