Skip to Content
0
Former Member
Feb 02, 2007 at 01:23 AM

Actual Overhead Calculation

1188 Views

Hi,

I prepared cost sheet with quantity and percentage based calculations. When i run the CK11N . The system is calculating the overhead correctly. After doing the production order confirmations, i found the overheads are not calculating. After running t.code KGI2 for the productions orders , the actual overhead rates are calculating. Is this the standard procedure. How to get the actual overhead calculation when i do the confirmations. Please help me.

Thanks

D.K.Lakshmi Narayana