Hai all..

Can any one give me a list of standard PP reports...?

Will be rewarded if helpful....

Regards,

Jhansi

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Here are some of the standard reports available for PP:

S_ALR_87099930 - Results of Costing Run

S_ALR_87099931 - Price vs Cost Estimate

S_ALR_87099932 - Variances Between Costing Runs

CK86_99 - Costed Multilevel BOM

CK80_99 - Cost Components

CK88_99 - Partner Cost Component Split

CK84_99_COST_ELEMENT - Cost Elements

CK84_99 - Itemization

KKED - Costed Multilevel BOM (Only Base Planning Object Exploded)

KKB4 - Itemization

S_ALR_87013036 - Multilevel Explosion of Base Planning Object

CK87_99 - Costed Multilevel BOM

CK89_99 - Cost Components

CK85_99_COST_ELEMENT - Cost Elements

CK85_99 - Itemization

S_ALR_87013046 - Material Cost Estimate vs. Preliminary Order Cost Estimate

S_ALR_87013047 - Cost Components

S_ALR_87013048 - Cost Elements

CK79_99 - Itemization

KKEC - Base Planning Object vs.Other Unit Cost Estimate

S_ALR_87013049 - Unit Costing Comparison

Susanth

6 REPLIES 6

Former Member
0 Kudos

check below site...it has everything about PP

http://www.sap-topjobs.com/SpecialPP/8431654645.html

Award Points...

Former Member
0 Kudos

Hi,

Check this link, it is having all PP standard reports

http://www.sapbrain.com/REFERENCES/StandardReports/SAP_standard_reports_list.html

Regards

Sudheer

Former Member
0 Kudos

Here are some of the standard reports available for PP:

S_ALR_87099930 - Results of Costing Run

S_ALR_87099931 - Price vs Cost Estimate

S_ALR_87099932 - Variances Between Costing Runs

CK86_99 - Costed Multilevel BOM

CK80_99 - Cost Components

CK88_99 - Partner Cost Component Split

CK84_99_COST_ELEMENT - Cost Elements

CK84_99 - Itemization

KKED - Costed Multilevel BOM (Only Base Planning Object Exploded)

KKB4 - Itemization

S_ALR_87013036 - Multilevel Explosion of Base Planning Object

CK87_99 - Costed Multilevel BOM

CK89_99 - Cost Components

CK85_99_COST_ELEMENT - Cost Elements

CK85_99 - Itemization

S_ALR_87013046 - Material Cost Estimate vs. Preliminary Order Cost Estimate

S_ALR_87013047 - Cost Components

S_ALR_87013048 - Cost Elements

CK79_99 - Itemization

KKEC - Base Planning Object vs.Other Unit Cost Estimate

S_ALR_87013049 - Unit Costing Comparison

Susanth

Former Member
0 Kudos

Hi,

check this site http://www.sapbrain.com/TUTORIALS/FUNCTIONAL/PP_tutorial.html

mark all helpful answers.

former_member181962
Active Contributor
0 Kudos

Hi Jhansikiran,

Go to se38, press * and press F4.

Click on the SAP Applications Button.

In the pop up, open the node PP to find the standard reports in PP Module.

Regards,

Ravi