Hi Gurus,

I am in the process of setting up sales set and the PO creation and goods receipt works fine.

However once I start testing the warehouse processes I face issues.

Sales set is exploded in PO but it doesn't get exploded in inbound delivery which restricts the follow on warehouse management movements.

We putaway in the warehouse first and the goods receipt is posted at last.

10 |10000 characters needed characters left characters exceeded

I am in the process of setting up sales set and the PO creation and goods receipt works fine.

Can you please elaborate what is Sales set and how do you set that into Purchase order and what are the steps you are following

0
We putaway in the warehouse first and the goods receipt is posted at last.

How are you doing that? Driving the interim bin negative? or this a business process that you are not able to replicate in WM?

0
* Please Login or Register to Answer, Follow or Comment.

2 Answers

avatar image
Former Member
May 10, 2017 at 01:09 PM
0

Hi,

Could you please confirm in which stage you face the issue? during the delivery creation, putaway, goods receipt, etc..also, what exactly the problem which you are facing?

Thanks,
Balaji

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member May 11, 2017 at 01:35 AM
0

Hi Balaji,

As mentioned, the problem starts in the inbound delivery creation itself, I don't see the components of the sales set in the inbound delivery which means I can't do the putaway for the components using LT03.