I need to set up quota arrangements- does anyone have documentation or instructions on how to go about it? Thanks

Raj Patel

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Posted on Jan 27, 2007 at 08:23 PM

    Transactionally very easy to do. What specific scenario are you looking for? Thats where they become tricky. If you can provide an example of what you want the quota arrangement to do, happy to help.

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 28, 2007 at 12:44 AM

    Hello Rajendra,

    Please find the link which gives very good idea about the Quora Arrangement.

    http://help.sap.com/saphelp_46c/helpdata/en/75/ee115f55c811d189900000e8322d00/frameset.htm

    Here is the example on how to use quota arrangement.

    http://help.sap.com/saphelp_46c/helpdata/en/f4/7d267944af11d182b40000e829fbfe/frameset.htm

    Hope this helps.

    Regards,

    Arif Mansuri

    Reward if answer is helpful.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 28, 2007 at 04:18 PM

    Hi Rajendra,

    Following are the prerequisites for Quota arrangement:

    1. Number of the material or the plant to which the quota arrangement applies

    2. Procurement type of the material

    3. Vendor number

    4. Quota arrangement validity period

    5. Quota to be assigned to each source of supply

    6. Special procurement type (if any)

    7. Check the Quota arrangement usage field in the purchasing or materials planning and control data of the material master record.

    If u have MRP set, then the requirements can be split among various vendors.

    Hope this helps.

    regards

    Anand.C

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 01, 2007 at 11:21 PM

    My specific requirements are

    scenario 1- quota to be divided into3 subcontractors - 70/20/10- FERT

    scenario 2- quota to be divided into 2 subcontractors 90/10- HALB

    where do I need to set config and quota arrangement

    Need help- Thanks

    Raj Patel

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.