Quota arrangements

Former Member
0 Kudos

I need to set up quota arrangements- does anyone have documentation or instructions on how to go about it? Thanks

Raj Patel

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

My specific requirements are

scenario 1- quota to be divided into3 subcontractors - 70/20/10- FERT

scenario 2- quota to be divided into 2 subcontractors 90/10- HALB

where do I need to set config and quota arrangement

Need help- Thanks

Raj Patel

Former Member
0 Kudos

Hi Rajendra,

Following are the prerequisites for Quota arrangement:

1. Number of the material or the plant to which the quota arrangement applies

2. Procurement type of the material

3. Vendor number

4. Quota arrangement validity period

5. Quota to be assigned to each source of supply

6. Special procurement type (if any)

7. Check the Quota arrangement usage field in the purchasing or materials planning and control data of the material master record.

If u have MRP set, then the requirements can be split among various vendors.

Hope this helps.

regards

Anand.C

Former Member
0 Kudos

Hello Rajendra,

Please find the link which gives very good idea about the Quora Arrangement.

http://help.sap.com/saphelp_46c/helpdata/en/75/ee115f55c811d189900000e8322d00/frameset.htm

Here is the example on how to use quota arrangement.

http://help.sap.com/saphelp_46c/helpdata/en/f4/7d267944af11d182b40000e829fbfe/frameset.htm

Hope this helps.

Regards,

Arif Mansuri

Reward if answer is helpful.

former_member214648
Active Participant
0 Kudos

Transactionally very easy to do. What specific scenario are you looking for? Thats where they become tricky. If you can provide an example of what you want the quota arrangement to do, happy to help.

Regards,