Hi All,
I need your support with the following can someone help.
This employee for example has 2 working days on the 19.03 and the 20.03 on his Work Schedule (IT0007)
However on the 19.03 he didn’t have clocks in out, but he has on the 20.03. The system should give then an error message (Tr PT_ERL00) that the employee was not at work on the 19.03.
The problem is that the system assigned the clock in / out to the previous days
since it is the first day to be processed, so then on the 20.03 it gave an error that
the employee was not at work.
But this is wrong, the error should be on the 19.03 and the assignment type should be = and not <
See below Screen shots.
Thanks,
Sharon
Instead of assigning a shift in IT0007, use IT2003. Evaluation the Time Evaluation Program (Tr PT60) and check the results.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.