on 05-09-2017 12:54 PM
we are having a problem with a specific material , when adding an extra line for an already existing component in a process order for this extra line the storage location and material staging indicator are not being filled. While the original line for this material does have this line.
We create a process order with a PV, we use control cycles and issueing storage location in the bom is filled. We only have this issue with one material. What could be wrong ?
I checked all obvious masterdata elements.
Hi, is the supply area is the same as the supply area of work center for that operation. Is control cycle maintained for same supply area . Check once in PK05 , what is the storage location for this supply area. If all these was maintained , check defUlt supply area maintained in mrp2 view of material master. If evrything is fine , check if the material is maintained in only one sloc or two different slocs. If so, that is confusing the system to pick up those details in prod order
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
sorry i made typing error
we are having a problem with a specific material , when adding an extra line for an already existing component in a process order for this extra line the storage location and material staging indicator are not being filled. While the original line for this material does have this information filled correctly.
We create a process order with a PV, we use control cycles and issueing storage location in the bom is filled. We only have this issue with one material. What could be wrong ?
I checked all obvious masterdata elements.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.