MRS 7.0 - MultiResource Scheduling Gantt Chart hour indicators

Is it possible to modify the indicators for hours in the Gantt Chart of MRS? In PS one can modify the planning board but it doesn't appear possible in MRS for some reason.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jun 07, 2017 at 09:25 AM

    Hi Donald,

    Yes you do have, on the GANTT tool bar you will see a button scaling factor, you can change that for Weekly / Monthly or Daily view.

    Also in the user setting menu there is a tab visible objects you can see the compressed view option there to see a more compact view, you can refer that documentation for more info.

    Best Regards,

    Mohammed.