Is it possible to modify the indicators for hours in the Gantt Chart of MRS? In PS one can modify the planning board but it doesn't appear possible in MRS for some reason.
Hi Donald,
Yes you do have, on the GANTT tool bar you will see a button scaling factor, you can change that for Weekly / Monthly or Daily view.
Also in the user setting menu there is a tab visible objects you can see the compressed view option there to see a more compact view, you can refer that documentation for more info.
Best Regards,
Mohammed.