I have one process chain running in production. I have a requirement to change the process chain schedule time.

I have some questions regarding this issue. Let us say my process chain is running at 1:30Am and i would like to make it run at 3:00 Am.

My process chain is loading data into Two ODS.

(1)These ODS's may be used in some other process chain's , Is there a way to identify other process chain using the same ODS's ?

(2) Say infoobject 0comp_code is used in ODS1 and ODS2 in two diffrent process chain . If they run at the same time , They does process chain fails?

(3) Say one Delta load is taking 20 Min for newly added 10000 record load.

If number of records becomes 40000 records , Then can i say it takes 80 min (approx) for 40000 records?