on 01-23-2007 4:34 PM
Hi,
Im my scenario, MRP will be running and planned orders will come.
It will be converted to PR,s.
Then after going to ME56 , we will assign vendor .
Then in ME58 , we will create the PR to PO.
If for some materials info records are not there , it is showing error and it is not allowing to assign vendor.
Is this the normal SAP settings ?
Kindly explain.
regards
You alter the std SAP settings by makeing the error message to warning messge for 06 341 in IMG of purchasing.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It's better to keep this settings becvaus eone side you are using ME58 means assign and process and other side you want the system should allow t oassing the vendor eventhough Info or contract is not there
anyway for message settings
SPRO-MM-Purchaisng-Environment data- define attributes of system messages
here you can look for that message and make to W (warning)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
If there is no Info record or outline agreement for a particular material, then in ME56 you can assign the vendor manually. This option is available in ME56 itself.
And then u can go ahead with ME58.
Hope this clarifies your doubt.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ME56 itself for assigning the source of supply that means you have created the source of supply in the system in form of Info records as minimum.
You cant proceed without info record.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.