Hello gurus:

I need guidance on the first consolidation of a year (I mean year 2)

Our customer has SAP ECC and has the following steps like business proccess:

1. End of year (ECC) and final consolidation of the year (31.12.year1)

2. In Januay year2, the client creates documents with special periods in year1 (period 13)

3. End of month in January of year2 and first cosolidation of the year.

Doubt is at this point,

Is it necessary to realize a new consolidation in month 12, year1?

What is the ideal process considering these documents in special periods?

Thanks for your help.

Best regards

Marco

Accepted Solutions (0)

Answers (4)

Answers (4)

lucas_costa3
Active Contributor

Hi Marco,

I personally prefer re-doing it in December as it keeps time dimension cleaner, and most of the time these additional periods will have adjustments only and not usual movements. This would also avoid changes in reports.

But again, it's a business decision. If they require to report delta changes in month 13,14,15 or 16 you need to add those to time dimension.

akos_beres
Contributor
0 Kudos

The other thing you can do is post the special period adjustments to period 12 with a different audittrail. This way they are in period 12 and also be able to report on them if you need to.

former_member287948
Discoverer
0 Kudos

Hi Vadim,

Can you please share your approach on how to handle special periods in SAP BPC NW considering that BPC only supports 12 months ?

Regards,

former_member186338
Active Contributor
0 Kudos

Please ask a new question and provide full details about your system!

marco_correa2
Participant
0 Kudos

Hi Vadim:

It's 10.1 NW version. But I suppouse that the proccess it's the same for both, isn't it?

Regards

former_member186338
Active Contributor
0 Kudos

No, things are different for nw and Ms version.... please remove ms tag.

In bpc you can have also extra periods after normal months or you can append extra periods to December.

former_member186338
Active Contributor
0 Kudos

Strange tags, what bpc version you are talking about - nw or ms?