on 05-08-2017 3:00 PM
Dear Experts ,
I have designed crystal report and scheduled in CMC . I scheduled same report for 20 times with different parameter values . Now i want to added two more filed in report . If i add it in report , CMC file will get auto refresh when source file get changed ? . Else i want to delete all scheduled reports and need to Re-schedule once again .
Please suggest .
Hi Sriram,
If it is a recurring schedule then choose the recurring schedule job in the history of the report and click more actions>reschedule and then "replace" and select "
Replace existing schedule" option and click on schedule again. If it takes effect well and good if not then you have to delete the existing schedule and then create a new one.
Regards,
Tanveer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mandar ,
Replace existing schedule wont help for my questions , By using that option,just we can change the schedule time , parameter value ,destination or whatever it is available under schedule .
Report wont get refresh . My issue is , after scheduled the report , if i did any changes in source path of the report , how to make affect in CMC folder path .
there is no need to schedule them again, unless you added any new prompts.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Looks like it might be bug. As long as there is no changes to report CUID, it should work. Try option, reschedule for one schedule, see if it works. If it works, I would suggest open a ticket with SAP support for further investigation.
Generally, it should work without a reschedule if you make any changes to the source report. We have seen in older versions like 3.1, this issue.
I have designed a report and saved in " D:Production_Report " Folder . After that i scheduled report in cmc . In CMC under folder option , i have created a Folder "Live" Right click "Add" -> local document and mapped file from a local server which placed under " D:Production_Report " Folder . Report scheduled on Daily basis . After completion of scheduling , i got few requirements to add 2 more fields in report .
Now i am updating report in source path (D:Production_Report Folder) , but its not reflecting in CMC . just i am receiving mail without changes .