Hello,

For a production facility, we measure the production reliability by calculating Schedule Attainment for each Product/Location ( compare Actual Produced Qty vs Planned Qty).

In IBP Inventory, how can one capture this supply variability in Safety Stock Calculation? Appreciate for all feedbacks and recommendations.

Thanks,

Tushar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member

Adherence = ABS (Actual Production Qty - Planned Production Qty)/Planned Production Qty

Production Lead Time CV (%) = 1.25 x (1 - Adherence) x PBR / PLT

Hi! Could you explain the 1.25 factor in the formula please?