Skip to Content
0

St. loc could not be changed in IBD after shipment cost document is created

May 05, 2017 at 07:04 PM

53

avatar image

Hi,

In Standard SAP, once shipment cost document is created, Storage location in Inbound delivery could not be changed. Is there any other way, where only the storage location can be changed prior to PGR even if SCD is created. Some OSS notes or exits, BADI's, if any, would be really helpful.

Regards,

Sat

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Jürgen L
May 07, 2017 at 10:08 AM
0

When you go into change mode do you then get a status message telling you that the options are limited because you have already follow on documents?

Share
10 |10000 characters needed characters left characters exceeded