Hi,
We are planning for a Upgrade from 4.7 to ECC 600, i need to know how can we able to calculate the downtime for the upgrade?
Thanks.
The production downtime is the period during the technical upgrade when the production system is out of service. The downtime period depends on various factors such as hardware power and size of the tables to be migrated, and is therefore contingent on each individual situation. SAP upgrade technology provides you with two strategy options: downtime-minimized strategy and
Resource-minimized strategy.
Characteristics of the downtime-minimized strategy:
Shorter production downtime
Parallel operation of production system and shadow system that enables the execution of as many upgrade tasks as possible during the uptime of the production system
Higher demand on system resources
Characteristics of the Resource-minimized strategy:
No parallel operation of production system and shadow system
Lower demand on system resources
Increased production downtime
SAP recommends that you perform the upgrade using the downtime-minimized strategy if a short production downtime is required.
For more details refer
http://service.sap.com/instguides
http://service.sap.com/erp-inst
Hope this will help you, do revert if you need further details.
Best Regards,
Sachin.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.