    Posted on Jan 11, 2007 at 11:21 AM

    Hi,

    If your creating the production order through manually means you will come to know when your doing the availability check, if the shortage appears as missing parts available you need to purchase those raw materials. If you run through MRP, system automatically calculate the net requirements and give the proposal for all the components.

    If your creating manually then you need to do all the procedure manually.

    Thanks and Regards,

    Satish

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 11, 2007 at 11:50 AM

    Hi,

    Make relevant settings in your order type for order creation.

    1. Order release nor allowed for missing parts (or)

    2. Order can be released despite missing parts.

    If after your order creation & release with material shortage, you need to arrange for sufficient stock (or) you can still make order confirmation and post goods movement for missing parts with COGI transaction later.

    Hope this will help you

    Regards

    Venugopal

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 11, 2007 at 02:50 PM

    To avoid the material shortage just when you create the production order you need to plan in advance. To plan in advance there are various options available in SAP based on what is your scenario and what kind of material you want to plan.

    For example You can use a sales forecast and demand management and MRP.

    Hope this helps

    Cheers

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.