how to achieve using bpm

Hi Everyone,

The scenario is, once the purchase orders are created in R/3 they are posted to third party system.There the third party system creates invoices for the corresponding PO and sends the invoices back to R/3. It involves validation of messages and triggering alerts.

How shall i approach this scenario using BPM.

Thanks in advance,

Sakthi

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2007 at 06:53 AM

    Sakthai,

    What is your third party system and how are you planning to connect XI with your third party system?

    Regards,

    Jai Shankar

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      For this u can use a 'switch' step in BPM.

      If u are planning to use sender RFC, then u need to go for Sync/Async bridge.

      steps:

      1. receive(open sync/async)

      2. switch (branches to vendors and conditions specified. Each branch may have a send sync step)

      3. send(Close sync/async, sends back response to RFC)

      Regards,

      P.Venkat

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2007 at 06:57 AM

    Hi,

    The probable steps in BPM are

    1. Receive

    2. send sync to third party systems

    3. validate response message using transformation step(if required separately)

    4. send step to R/3

    Regards,

    P.Venkat

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2007 at 07:01 AM

    steps would be like

    Receive step to receive Order from SAP, call synchronously third party system, check the response from third party and trigger alert in case of problem, call SAP(send step) to post invoice.

    --Archana

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 10, 2007 at 07:22 AM

    Sakthi,

    Do you mean to say that for the receiving Invoice needs to be validated against the Sending PO?

    First of all:

    I guess Invoice will be generated not immediately after PO creation and it may take a few days.. That case I don't think BPM will be a wise choice.

    I think it will be good if you handle this validation in the receiving R/3 side..

    Thanks,

    Himadri

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.