cancel
Showing results for 
Search instead for 
Did you mean: 

process order confirmation quantity

Former Member
0 Kudos

Dear friends,

I am working with process industry. My order type is PI01. Control key PI01.

In material master in "work scheduling" view, i have maintained production scheduling profile as"000001". ( in t.code OPKP--i have activated "Auto GR indicator).

In material master MRP2 View ihave maintained Prod store location also.

I have created my BOM in CS01 for process industry.

Now i am confirming my order in CORZ, in my last phase, i am expecting my finished goods also automatically to move.

<b>But the system is not bringing the finished goods</b>. Why?

It is bringing only my BOM components (means semi finished goods). Even for my semi finished goods, it is not bringing the BOM Quantity. I am manually inputting the quantity for my semi finished goods.

<b>

Why the system is not bringing the quantity for my semifinshed goods?</b>

(I<b> have maintained maste rrecipe for my finished goods only,not for semi finished goods)</b>

Thanks

Senthil

Accepted Solutions (0)

Answers (1)

Answers (1)

mallikharjunrao_thota
Active Participant
0 Kudos

Hi ,

In the customization for confirmation parameters for process orders , in the genral valid settings screen , tick the goods movements for all components feild that will solve your problem ,

regards ,

mallikharjun

Former Member
0 Kudos

Hi,

It is not working