Dear Experts,

In my issue sub contracting charges is not calculating in CK11 however it is showing in CK11N. Thus what i have to do so that sub contracting charges will be reflecting in CK11. Your prompt response will be highly appreciated.

Thanks & Regards,

Varun Kumar

Accepted Solutions (0)

Answers (1)

Answers (1)

pavan_kumar18
Employee
Employee
0 Kudos

Hi,

let me know the error in detail, as you are saying sub contracting charges are showing but not calculating.

What error you are getting at the time of calculation...?

how you are tracking the sub contracting charges, what method you have used for that..?

Regards,

Pavan Kumar Arvapally

former_member282631
Participant
0 Kudos

Hi Pawan,

Thanks for your prompt response.

My issue is that subcontracting charges is not showing in CK11. Kindly find below snap for your reference :-

So kindly suggest how can i fetch sub contracting cost here.

Thanks & regards,

Varun Kumar

pavan_kumar18
Employee
Employee
0 Kudos

Hi,

Please check the Cost elements assignment in OKTZ related to subcontracting.

Regards,

Pavan Kumar Arvapally

pavan_kumar18
Employee
Employee
0 Kudos

Hi,

Please look into the Valuation variant used for the costing variant:

There you can find the strategy sequence for picking the price which is related to Sub contracting.