Production order variances settlement (categorie problem)

0 Kudos

Hi experts ;

When i'm settling production order to CO-PA and after doing KKS2 in order to determin the variances , i have noticed some inconsistency in the variance categories that are used by the system. For example , a variance that is caused by input price variance are allocated to remaining input variance ;

Please help me find the origin of the problem ;

Thanks in advance for your help.

Accepted Solutions (0)

Answers (3)

Answers (3)

pavan_kumar18
Advisor
Advisor

Hi,

Adding points to the Hemanth,

Check the Cost element assignments in PA Transfer Structure.

Regards,

Pavan Kumar Arvapally

Hemanthkumar
Active Participant

Dear Morad Khalfi,

There could be two possiblities for this

1. If you dont flag input price variance checkbox in Variance variants -OKVG, it would be allocated to remaining input variance.

2. From Pa transfer structure side, you might have mapped the input price variance and remaining input variance categories to same value field.

Best Regards,

Hemanthkumar

0 Kudos

Hi experts ;

Thanks for your response , nevertheless , i have already checked OKVG and KEI1 , they are both good ;

Best regards.