Picking date determination in STO delivery

Hi, I have an issue with picking date determination in STO delivery (delivery type = NL).

For example, i create a STO with delivery date falls on sunday, with planned delivery time of one day, the delivery creation date in the STO falls on saturday. I expect my transportation plng date and picking date to fall on saturday where as it falls on friday. The calendar is set to 365 days free days. We have shifts and all three shifts are assigned to all week days.

Can anyone let me know what i may be missing

Thanks/Jag

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 09, 2007 at 09:17 AM

    Delivery scheduling takes into account the following times

    Tranit Time

    Loading time

    Pick/Pack time

    Transportation Lead time

    1. Check Pick/Pack time for the shipping point in IMG-LE-Basic Shipping Functions-Scheduling-Maintain Duration, also check if the data is being defaulted from shipping point or routes.

    2. Check as to how the Routes data is set-up.

    Regards,

    Gauravjit

    Reward Points if solution is helpful

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.