05-02-2017 4:46 PM - edited 02-03-2024 9:14 PM
Dear SAP experts,
we´re scheduling the transfer from SOP (infostructure S076) to demand management with the reports RMCP6RES / RMCP6BIN in the background.
The variants for the job has been created with MC8E.
Unfortunately now we´ve found some parts, where the transfer from S076 to demand management is not possible. The transfer for manufactured parts does not cause any problems, it seems that only the transfer for Buy parts (which are sold as trade goods to the customer without production orders) is not possible.
If we´re forcing MC8E to do the transfer just for one of those special material numbers, SAP always creates the message MA401 "no data exists for chosen selection".
If we´re doing the transfer manually using TX MC74, the demand is transfered without any problems.
We didn´t find any differences in the material master between Make and Buy parts, they´re using the same strategy Groups, etc.
S076 has values maintained for all of the parts, no difference there.
Did anyone had the same problem and solved it? Thanks!
The correct reference to the SAP Note is 500354 instead of 500534.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Problem solved. 🙂 The main problem was, that the affected material numbers are missing the entries in S076E.
For this issue, there is a SAP note existing - 500534. After executing the report RMCPSOP, table S076E was updated with the missing entries and the transfer of the planning worked fine in the Background.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.