Value flow/ quantity flow in Proc. Param tab for material in CJ20N

May 02, 2017 at 10:44 AM

38

avatar image

Hi All ,

I am creating FG by assigning assgin material -ve quantity to activity , then do the cofirmation by CN25 to bring the FG in stock . But now when I am doing confirmation by CN25 FG comes in stock under Unrestricted stock not the project stock .

I check in CJ20N where the material is assigned Value flow/ quantity flow fields are not flowing . I think because of that my stock seen under Unrestricted Stock . Check the attached screen .

capture-1.jpg

capture-1.jpg (44.9 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Virendra B May 03, 2017 at 05:21 AM
0

Hi All,

Issue resolved by assigned correct procurement Indicator to material , now values are flowing .

Thanks ,

Virendra