Value flow/ quantity flow in Proc. Param tab for material in CJ20N

former_member249141
Participant
0 Kudos

Hi All ,

I am creating FG by assigning assgin material -ve quantity to activity , then do the cofirmation by CN25 to bring the FG in stock . But now when I am doing confirmation by CN25 FG comes in stock under Unrestricted stock not the project stock .

I check in CJ20N where the material is assigned Value flow/ quantity flow fields are not flowing . I think because of that my stock seen under Unrestricted Stock . Check the attached screen .

capture-1.jpg

Accepted Solutions (1)

Accepted Solutions (1)

former_member249141
Participant
0 Kudos

Hi All,

Issue resolved by assigned correct procurement Indicator to material , now values are flowing .

Thanks ,

Virendra