Hi,

I need to get the expenses for all the projects. The information for each expense should have the time and the charge code associated. Where can I get this information from? I would prefer to call a function module, or go directly to the tables/views.

I also need budget information per project (planned/actual).

I'm using SAP R/3 Enterprise

Many thanks,

Petru

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 08, 2007 at 01:53 PM

    Please use tcod ' S_ALR_87013531'

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2007 at 07:26 PM

    Dear Petru,

    Look the followings reports:

    Budget : S_ALR_87013557 or S_ALR_87013558;

    Expenses : S_ALR_87013545 this report list the actual costs per Cost Element/Period/Year;

    Best Regards,

    Elza

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 08, 2007 at 02:53 PM

    Hi!

    You may want to consider the use of transaction RKACSHOW.

    You will be able to have a direct view on all the CO relevant tables.

    Once in the report, with menu Goto>Budget/plan values, you will be able to analyze the budget relevant tables.

    Regards

    Martina

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 08, 2007 at 05:11 PM

    S_ALR_87013531 causes an error and triggers a small dump on my system.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.