on 05-06-2017 2:32 PM
Hi,
I'm implementing MDG solution to maintain WBS and Projects. I have a scenario where I need to "Update Multiple different Project Statuses in a single LUW". I do not have direct control on the COMMIT as MDG framework handles it.
I've tried using "BAPI_BUS2001_SET_STATUS" with its 'BAPI_PS_INITIALIZATION' and 'BAPI_PS_PRECOMMIT' calls.
I've tried various alternative sequence of calls (without success) to the above bapis inside and outside the LOOP. e.g. With repeated initialization without a commit, only the last Project's changes are committed.
Is there an altertive solution? For instance, another BAPI I may be missing that performs mass changes on Project Status.
In the case of Project/WBS 'attributes', I'm all set as BAPI_PROJECT_MAINTAIN is a lifesaver there. Is there similar one for Status?
Regards,
VS
Hi VS,
My client planning to implement MDG for PPM/PS and trying to find information if you can share details about your implementation to my gmail which is ficoshree would be gr8.
Thanks,Sreeni
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
try using BAPI_BUS2054_SET_STATUS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.