on 05-02-2017 12:49 PM
Hello,
I have to start using Capacity planning in my factory. But the workcenter capacity have been setting without considering real capacity. Despite that, I can't change the capacity configuration because it would change the scheduling.
I thought I could use "fake" workcenter with the accurate capacity, linked them to the real workcenter that receive the demand throught a hierarchy. with the cumlation of requirement capacity, it,s working.
But now, they are asking me to create bigger hierarchy, representing a section of the factory. I consider creating a hierarchy of 3 levels ( level 1 : root, level 2 : fake workcenter, level 3 : Workcenter with requirement capacity). Is is possible to cumulate capacity requirement from level 3, but the available capacity from level 2 ?
Thanks
Hello Marine,
SAP standard functionality allows resource hierarchy calculation only for 2 levels. The following links might be helpful to you.
https://archive.sap.com/discussions/thread/3856519
https://archive.sap.com/discussions/thread/3823242
Regards
AK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.