Updating projects when updating template

Former Member
0 Kudos

Hi,

I thought I remembered that it is possible for the system to update the structure of a project when the template it is build on is updated, but I can't remember where to set this. Any suggestions?

Regards Camilla

Accepted Solutions (0)

Answers (2)

Answers (2)

schneidertho
Advisor
Advisor
0 Kudos

for standard WBS not possible

for standard network, there should be a function in the menu to get the new activities/components

cheers

thorsten

Former Member
0 Kudos

As far as I aware, the effect of changes in template will come only for new creation but system will not over-write created projects with changes in template.