Hi Community,

I would like to ask you about the required team to deploy a Hybris C4C project. Basically we are thinking in deploy the basic utilities of the solution, that means Sales, Marketing and Service. Thanks in advanced for your replies.

Carlos

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    May 01, 2017 at 10:20 AM

    Hello Carlos,

    5-member team should be enough to start a project even if we want to integration and roll out.

    Project manager, 1 or 2 SAP C4C Functional Consultants, 1 or 2 SAP C4C Technical Consultants and

    1 SAP PI Integration Consultant.

    By fallowing SAP cloud Launch or SAP Hybrid implementation methodology, project delivery should not take longer than 3-6 Months, depending on the complexity and scope of the solutions.

    If this answer satisfy your query, then please do not forget to click on“Accept” this answer as correct one.

    Thanks

    Santosh

    Add comment
    10|10000 characters needed characters exceeded

  • May 02, 2017 at 09:29 AM

    Carlos,

    There is no defined rule for number of resources required for a Project, be it Hybris C4C project as well, however, having said that:

    1. Assuming there is no integration and no Custom development (using SDK) involved, with Customer's data of a medium size and an average user base to be migrated on C4C approx .50, it should not take more than 2 months based on the assumptions mentioned. You can do away with 2 Consultants - 1 Solution architect/Functional SME and another full time Functional Consultant. Project management can be a role which the Architect too can play or you can have one part time.

    2. If its C4C implementation with integration to SAP ECC OnPrem or SAP CRM OnPrem - only standard OOB integration, no custom development/enhancement, then for same number of users mentioned in point 1 above, it should not take more than 12 - 16 weeks. You will need: Sol.Architect = 1;

    Project Manager = 1

    Functional Consultant = 1

    Part time ECC Consultant = 1

    PI/HCI consultant = 1 (FT)

    BASIS and Network/Security = 1 (part time)

    3. For a Project, where point 2 along with Custom development/enhancements are involved, you will in addition to above resources should add 1 or 2 Technical developers (SDK) and you cannot really estimate the time unless you actually have the requirements for Custom Dev. so basically this type will be 12 - 16 weeks plus Effort requirement for Custom Dev.

    Hope this gives you some idea to get started.