Production order Basic end date change automatic one day before.

Apr 30, 2017 at 05:50 AM

60

avatar image
Former Member

Hello Guys,

When I manually creating production order using BACKWARD scheduling after entering basic end date is changes automatically one day before. which is affect my rescheduling through std. FM (BAPI_PRODORD_CHANGE). Can anyone tell why this basic end date is changing one day before as enter end date.

Ex - Order Basic end is 05/11/2017 as i want but it changes automatically to 05/10/2017 when manually creation of production order.

10 |10000 characters needed characters left characters exceeded

Are you saying that the basic date you entered is automatically changing or that the scheduled date is changing? Is any message generated when it changes the date? First thoughts are to check scheduling margin key (float after production) or GR processing time but I checked both of those in my system and while they influence the scheduled date that is calculated by the system, they do not influence the basic end date that was entered. I guess it could also be something in the factory calendar but that usually generates a message that the date entered isn't a work day (plus, changing from 5/11, a thursday, to 5/10 a wednesday doesn't make sense.

0
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
May 02, 2017 at 06:10 PM
0

Hello

This question has been already asked in SCN. Take a look on the following thread for details:

https://answers.sap.com/questions/172790/inhouse-production-time-in-material-master-changes.html

Regards,

Caetano