collective confirmation of production order

Apr 29, 2017 at 10:16 AM

98

avatar image
Former Member

Hi

I see a reply to use the T code CORR for collective confirmation .

My question is, if there are any F30 items below E procurement type, how does this work ? Will all the F30 parts below E also get posted ?


10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Solomon Macwan May 02, 2017 at 05:03 AM
0

Hi Venkatesh,

sorry, didnt get your question. What is F30 items?

Regards,

Soloon

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member May 03, 2017 at 12:58 PM
0

Hi

Procurement type in material master is defined as F and special procurement type is defined as 30. This procurement type is used for Job work.

does this answer your question.

Share
10 |10000 characters needed characters left characters exceeded
Caetano Almeida
May 03, 2017 at 01:26 PM
0

Hello

Special Procurement 30 is the subcontracting, which means that you will have job work processed outside.

In this case, system generates a purchase order instead of a production order and you don't post a confirmation for a purchase order.

You will only post the goods receipt for the PO in MIGO, where the components will be also consumed.

Regards

Caetano