Skip to Content
avatar image
Former Member

Stopping the Production planning during client shutdown period .

HI Experts,

I have an requirement where customer is asking for a way in which the production planning needs to be stopped during client shutdown period ( E.g. : July and December month for 2 weeks).

How can i fulfill the requirement ?

One of the methods which i have read in one of the SCN threads are to define shutdown period in the factory calendar which will restrict the planning during the defined period and will provide the delivery date after this period.

Is there any alternate method to do so

Thanks in advance.

Regards,

Sanket gadhe

Add comment
10|10000 characters needed characters exceeded

  • Former Member

    Requirement :

    I need the system to recognise that there will be periods where there will be no manufacturing, therefore the system need to allow for the shutdown which might mean bringing batches forward to avoid possible stock outs etc eg. if there are 4 batches required for 1 material over 2 months, then we specify that 3 weeks over this 2 month period will be a shutdown period, then the system needs to adjust accordingly and bring batches forward to cover the 3 week shutdown

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 25, 2017 at 02:28 PM

    Usually we lock all users & stop background jobs, interfaces, etc during shut down period.

    If requirement is to restrict only shop floor folks (& identifying all of them is not easy) then only configuration changes are advisable.

    Add comment
    10|10000 characters needed characters exceeded