on 12-26-2006 10:36 AM
Hello Experts,
In the Service Request, I have set the Date Rule for "Requested End" date for 4 days from "Requested Start" date. What I want is, the system should exclude the week-ends while calculating the Requested End date. How do I achieve this???
Many Thanks in Advance.
SP.
Hi SP
If you want to add company holiday to take in account while calculating End date then config for Factory calendar / Holiday
SAP Implementation Guide> SAP Web Application Server>General Settings-->Maintain calendar
Once u done with config, use FM BUSINESS_DATE_CREATE for End date creation.
hope you able to get your result.
Thanks,
Deven
Do not forget to allocate points.............
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi SP.
You use reference object in your date rule. You can refer to below helps.
http://help.sap.com/saphelp_crm50/helpdata/en/d9/fce93a29768802e10000000a11402f/frameset.htm
I am also looking for the solution for a more complex senario of date managment. I am still headached on it.
Best regards,
Allan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.