Skip to Content
0

BOM explosion at PR without validating configuration.

Apr 27, 2017 at 11:36 AM

36

avatar image
Former Member

Hi All,

Subcontracting PRs created with respect to sales orders for configurable materials. However system consider all the components during BOM explosion at the time of PR creation. Business expect it should explode only configurable components during PR creation.

For EX :

Material BOM contains 5 components, at sales order configuration level, we selected only 2 components, but at PR level BOM exploding 5 components and subsequently consumption happened for all the 5 components during goods receipt.

Please share the required configuration/steps to be performed for this requirement.

Thanks in advance.

Santosh

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Jürgen L
Apr 29, 2017 at 08:06 PM
0

You may find your answer in the OSS note 588117 - FAQ: Configurable materials in purchasing

Share
10 |10000 characters needed characters left characters exceeded