on 12-24-2006 7:01 AM
Hi,
I have created a gereic datasrc using view & i took the following fields
MATNR Material
WERKS Plant
PBDNR Req.plan number
BDZEI Reqmts pointer
LAEDA Last change
MEINS Base Unit
FIXMG Planned qty
In the transfer rules of BW the system gave mapping only for LAEDA Last changewith the infoobj 0CH_ON,so I took 0mat infoobj formapping with Matnr
0plant for werks & created ZpBDNR,ZBDZEI for PBDNR BDZEI & for FIXMG i mapped with the infoobj 0PRDPLN_QTY
In the monitor screen it is showing me 0 records with status yellow then I went to the job overview it is giving me the following msg in job overview
Date Time Message
24.12.2006 12:18:13 Job started
24.12.2006 12:18:13 Step 001 started (program SBIE0001, variant &0000000006181, user ID ALE_MASTER)
24.12.2006 12:18:13
24.12.2006 12:18:13 DATASOURCE = PLANEW
24.12.2006 12:18:13 *************************************************************************
24.12.2006 12:18:13 * Current Values for Selected Profile Parameters *
24.12.2006 12:18:13 *************************************************************************
24.12.2006 12:18:13 * abap/heap_area_nondia......... 2000000000 *
24.12.2006 12:18:13 * abap/heap_area_total.......... 2000000000 *
24.12.2006 12:18:13 * abap/heaplimit................ 40000000 *
24.12.2006 12:18:13 * zcsa/installed_languages...... DE *
24.12.2006 12:18:13 * zcsa/system_language.......... E *
24.12.2006 12:18:13 * ztta/max_memreq_MB............ 250 *
24.12.2006 12:18:13 * ztta/roll_area................ 2000000 *
24.12.2006 12:18:13 * ztta/roll_extension........... 2000000000 *
24.12.2006 12:18:13 *************************************************************************
24.12.2006 12:18:14 Could not determine BW release of logical system 'QEMCLNT003'
24.12.2006 12:18:14 Job cancelled after system exception ERROR_MESSAGE
Thanks,
Maya
Hi maya,
There is a connection problem to your connection from R3 to BW.Kindly check it .
KK.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Maya,
Check in RSA3 whether your view is pulling data .if yes, Check your RFC from R/3 to BW . Check the Logical names of the clients ..
Thanks
Krish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you created Logical system also? If not you have to create logical system and assign it to ur source system.
If u on BW3.5 system:
Tcode SPRO->ref Img->SAP NetWeaver->SAP BI->Links to other systems->define logical system. (not sure abt path...but it must be somehow similar to this only)
Check this link it may help you:
http://www.erpgenie.com/sapgenie/docs/MySAP%20BW%20Cookbook%20Vol%202.pdf
Message was edited by:
KJ (Kamaljeet)