I am seeking a method of design to cascade the individual process order requirements for the same raw material to be used on the same day into separate recommendations in MD15.
For example :
Finished Product A & B process orders:
Both Products contain raw material 123
Raw material 123 for both process orders are due on 12/20, with an order start date of 12/15.
How can I view MD15 separately for every requirement as a separate Planned Order for two process orders?
Hi Pravin
Try with availability check field '02" indivividual requirement for the ROH material material master.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can someone share with me how this was solved.
I have the same issue I have 4 end items using the same component e.g. item 1, 2, 3, 4 uses component X. All orders have the same start date as we start our production on Monday. So all four dependent requirements land on Monday and I get one planned order clubbed together for the total amount of the 4 dependent requirements.
I have followed the suggestions here to no avail. The only way I can see handling is via custom code or I can make my start dates Monday through Thursday which will create separate planned orders.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
If you firm the purchase requisition for the first created one manually
the second purchase requisition will be created on the same day itself(no clubbing)
ie Two PR for different reqmts of FERT for the same raw mat on a single day
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Pls check in the Material master in MRP 4 view you have given the Individual/ Collective indicator 2. If you have given that it will club the requirements.
Thanks and Regards,
Satish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Satish,
As you suggested, we have already made these changes as MRP 4 view Individual?collective as "01".
Here my case is specific to Dep. Requirement gets generated as Individual requirement on daily basis,if only one Dep Requirement falls on that day,but on particular day if there more than one Dep. Requirement are there then it gets clubbed.....
Hi Reddy & Hemant
This availability check field '02" indivividual requirement & Lot size procedure as "EX" for the ROH material material master is already there.My issue is "It creates the dependent requirement if there is only one on particular day but if there are more than one, then on that day all those gets clubbed.....
Thanks for earlier suggestions......
With warm regards,
Pravin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pravin,
Define "EX" is the lot size in material master in MRP view.
regards
hemant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.