I am seeking a method of design to cascade the individual process order requirements for the same raw material to be used on the same day into separate recommendations in MD15.

For example :

Finished Product A & B process orders:

Both Products contain raw material 123

Raw material 123 for both process orders are due on 12/20, with an order start date of 12/15.

How can I view MD15 separately for every requirement as a separate Planned Order for two process orders?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Pravin

Try with availability check field '02" indivividual requirement for the ROH material material master.

Regards

YMREDDY

Answers (6)

Answers (6)

Former Member
0 Kudos

Can someone share with me how this was solved.

I have the same issue I have 4 end items using the same component e.g. item 1, 2, 3, 4 uses component X.  All orders have the same start date as we start our production on Monday.  So all four dependent requirements land on Monday and I get one planned order clubbed together for the total amount of the 4 dependent requirements.

I have followed the suggestions here to no avail.  The only way I can see handling is via custom code or I can make my start dates Monday through Thursday which will create separate planned orders.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Jeremy

Please open a new thread describing your issue instead of posting to old threads.

BR

Caetano

Former Member
0 Kudos

Answered

Former Member
0 Kudos

Hello,

If you firm the purchase requisition for the first created one manually

the second purchase requisition will be created on the same day itself(no clubbing)

ie Two PR for different reqmts of FERT for the same raw mat on a single day

Thanks,

nandha

Former Member
0 Kudos

Hi,

Pls check in the Material master in MRP 4 view you have given the Individual/ Collective indicator 2. If you have given that it will club the requirements.

Thanks and Regards,

Satish

Former Member
0 Kudos

Hi Satish,

As you suggested, we have already made these changes as MRP 4 view Individual?collective as "01".

Here my case is specific to Dep. Requirement gets generated as Individual requirement on daily basis,if only one Dep Requirement falls on that day,but on particular day if there more than one Dep. Requirement are there then it gets clubbed.....

Former Member
0 Kudos

Hi Pravin

Try this.

In lot sizing procedures. there is lot size called Daily lot size" TB".

You copy this lot size into Z lot size .

Change the field "no.of periods " to "1"

do not change any other fields.

Use this new lot size in the lot size key of ROH.

It should definitely work.

Regards

YMREDDY

former_member189817
Active Contributor
0 Kudos

Hi,

Set individual requirment for thae raw material 123 in MRP 4 screen.You no need to change MRP type and all.This will generate two diffrent PR or Pln. ord . for material 123 even though their req falls on same date.

Message was edited by:

velmurugan s

Former Member
0 Kudos

Your problem will be solved with lot size procedure EX only. There is no other alternative.

Regards

TAJUDDIN

Former Member
0 Kudos

Hi Reddy & Hemant

This availability check field '02" indivividual requirement & Lot size procedure as "EX" for the ROH material material master is already there.My issue is "It creates the dependent requirement if there is only one on particular day but if there are more than one, then on that day all those gets clubbed.....

Thanks for earlier suggestions......

With warm regards,

Pravin

Former Member
0 Kudos

Hi Pravin,

Define "EX" is the lot size in material master in MRP view.

regards

hemant